Boys & Girls Club Renovation Project

Boys & Girls Club Renovation Project Rendering
Boys & Girls Club Renovation Project Rendering

Department/Division Served

Boys and Girls Club

Use

Community Development

Current Status

Planning & Design

Description

The Boys & Girls Club Renovation Project consists of a full renovation of the 2-story structure at 296 Moache Circle, previously known as the Peaceful Spirit Building. The renovation will include a full replacement of the HVAC system, new roof, windows and exterior façade, a full renovation of the interior, as well as extensive landscaping and exterior improvements.

Project Team

Design Team: Reynolds, Ash + Associates
Construction Manager: FCI Constructors

Project Budget

$8,000,000

Funding

Southern Ute Indian Tribe

Completion Date

January 2028

To top