
Main Office
970-563-0138
Mission
The Construction & Project Management Department is committed to carrying out, in a professional manner, the needs and visions of the Southern Ute Indian Tribe related to the planning, design, and construction of tribal projects.
Active Projects
Cedar Point Housing Initiative
- Project Description: This project entails civil design for twenty-three home sites, as well as design-build for twenty-five townhomes, new road(s), and additional infrastructure, and a new park for the residents at Cedar Point.
- Project Start Date: Fall 2015
- Project Completion Date:
- Phase 1A Construction Completed Summer 2017
- Phase 1B Civil Construction Complete Winter 2017
- Townhomes will be Complete Summer 2018.
- Design Project Completion Percentage:
- Master Infrastructure Report 100% Complete
- Phase 1A Design 100% Complete
- Phase 1B Design 100% Complete
- Townhome Design 100% Complete
- Design Firm:
- Russell Planning & Engineering (Master Infrastructure Report, Phase 1A Construction, Phase 1B Construction, Conceptual Phases)
- Reynolds Ash + Associates (Townhomes)
- Contractor: FCI Constructors, Inc.
- Cedar Point Housing Initiative Phase 1A Construction
- Cedar Point Housing Initiative Phase 1B Construction
- Cedar Point Housing Initiative Townhomes
- Location: Cedar Point Subdivision

KSUT
- Project Description: This Project entails the design renovation of the old Sky Ute Casino purchasing building, which will be occupied by KSUT.
- Project Start Date: Fall 2014
- Project Completion Date: TBD
- Design Project Completion Percentage: 100%
- Design Firm: Reynolds Ash + Associates
- Construction Completion Percentage: 0%
- Contractor: TBD
- Location: Old Sky Ute Casino Purchasing Building
SunUte Office HVAC Replacement
- Project Description: This project entails providing replacement of the office HVAC unit at the SunUte Community Center. C&PM is working closely with Building Maintenance as the project moves from a completed design into construction.
- Project Start Date: January 2017
- Project Completion Date: TBD
- Design Project Completion Percentage: 95%
- Design Firm: QA Engineering, LLC
- Construction Completion Percentage: 0%
- Contractor: TBD
- Location: SunUte Community Center
CR 517 Road Improvements
- Project Description: This is a joint project between the Tribe, La Plata County, and CDOT that incorporates signalization at HWY 172 & CR 517, curb and gutter from HWY 172 to Howe Drive, pedestrian improvements, bicycle paths, crosswalks, and a new left turn lane.
- Project Start Date: October 2015
- Project Completion Date: Summer 2018
- Design Project Completion Percentage: 100%
- Design Firm: Russell Planning & Engineering
- Construction Completion Percentage: 99%
- Contractor: Crossfire, LLC
- Location: CR 517

HWY 160 Wildlife Overpass/Underpass
- Project Description: This project is in conjunction with C&PM, Tribal Planning, Wildlife, and CDOT, and entails installation of one wildlife underpass and one wildlife overpass at HWY 160 & HWY 151.
- Project Start Date: Spring 2018
- Project Completion Date: TBD
- Design Project Completion Percentage: 30%
- Design Firm: Bechtolt Engineering, LLC
- Contractor: TBD
- Location: HWY 160 & HWY 151
Recently Completed Projects
SU 106 End of Trail
- Project Description: This was a BIA-638 project and is re-construction of .6 miles of roadway.
- Project Start Date: June 2013
- Project Completion Date: Spring 2017
- Design Project Completion Percentage: 100%
- Construction Project Completion Percentage: 100%
- Design Firm: Souder Miller & Associates
- Contractor: Old Castle
- Location: End of Trail Road
Return to Departments